Malaysia facility update | Construction underway at new 53,000 sq ft site
Michael Bedard2026-11-18T16:17:16+00:00Construction has begun on the lounge, offices, Smart Warehouse, and 10K and 100K cleanrooms at our new Malaysia facility. The site spans 53,000 sq ft across Lot 8 (33,000 sq ft) and Lot 6 (20,000 sq ft), adding 31,000 sq ft of production space compared with the current 22,000 sq ft facility.
More capacity for prototypes and volume production
Two additional surface-mount technology (SMT) lines will bring the total to four. One line will support new product development and prototyping, and three will support mass production. The facility will also have three backend production lines for FDMX, AOVX, and Skyhawk.
Monthly capacity is expected to roughly double, from about 90,000 to 180,000 units, depending on SKU mix. The Smart Warehouse will support material flow and traceability, while a plant-wide manufacturing execution system (MES) integrated with SAGE will provide live visibility into production KPIs and costing.
Certifications and staffing
The Malaysia operation will maintain its ISO 9001 and ISO 13485 certifications. The expansion also includes an LMW license and DOE, DOSH, CCC, and COO requirements.
The staffing plan projected about 161 employees by the end of August 2026, with headcount expected to trend toward 150 depending on sales growth, SKU mix, and automation.
Project milestones
The Phase 3 schedule targeted September 2026 for construction and setup of SMT lines 3 and 4. Phase 4 covers relocation, validation, and qualification, with work scheduled for October through December 2026.